11 February 2026
For informational purposes only. Not investment advice.
TAKE or BREAK (executive summary)
TAKE (supports our thesis): Last week, all four major hyperscalers reported Q4 2025 earnings. In a nutshell: aggregate 2026 capex guidance came in at $670-715B, a 46-62% increase over 2025 actuals and 27-35% above Wall Street consensus.
Whilst Wall Street experienced sticker shock, the crucial element for our thesis is that every hyperscaler independently confirmed what we’ve been saying: they are supply-constrained, not demand-constrained.
So in effect, the causal chain we laid out in our 2026 Outlook is playing out exactly as described: demand outstrips supply → capex accelerates → spend broadens. The thesis is very much intact.
BREAK (forces a reassess): As always, we have to remain vigilant for things that might break our thesis. Top of mind is: if the capex spend doesn’t convert downstream; specifically, if cloud backlog growth decelerates materially without supply constraints as the explanation (e.g., if the new DeepSeek model to be released next week changes unit economics of the hyperscalers substantially). Or if any major hyperscaler pivots language from “capacity build” to “optimise/pause.”
Based on comments from the earnings calls, we do not see this situation manifesting any time soon. However, we will monitor a >10% downward revision to forward capex guidance from any of the big four as a credible early re-assessment flag.
Context: The market flinches, but the cheques keep getting bigger
As we wrote in last week’s Thesis Takes or Breaks, the mega-cap tech trade is being repriced: the market has stopped paying for “AI exposure” and started demanding “AI ROI.” This will not be news to you if you’ve been holding hyperscaler stocks over the past three months: the tape has been uncomfortable.
We get the scepticism. And this time, the discomfort isn’t just narrative; it’s fundamental. Last week Amazon, Microsoft, NVIDIA, Meta, Google, and Oracle collectively lost over $1 trillion in market value. Microsoft experience the largest drawdown with c.$430B wiped out and Amazon experienced c.$300B.
Table 1: Q4’25 Stock Reactions
Source: Market data, earnings reactions (Jan-Feb 2026)
The reactions tell you where the market’s head is at: Apple, the company spending the least on AI, outperformed. NVIDIA, the company that sells the infrastructure, rallied. The hyperscalers writing the cheques got punished.
Why?
Because the sheer scale of the capex commitments is compressing free cash flow across the board. These have historically been the greatest cash-generating machines in corporate history.
In 2026, that changes: Amazon, which generated just $11.2B in FCF last year (already down 70% YoY), is projected to swing to negative $17-28B. Google’s FCF is expected to collapse 89%, from $73.3B to roughly $8B. Microsoft’s is forecast to decline 28%, from c. $74B to c. $53B.
Table 2: Hyperscaler Free Cash Flow Outlook
Source: Company filings (2025 actuals); Morgan Stanley, Bank of America, Pivotal Research, Barclays (2026 analyst estimates, Feb 2026)
This fundamentally changes the picture on what have traditionally been seen as money printing machines and this is why we wrote last week that the era of “park-it in-Mag-7-and-forget” is coming to an end and investors will now need to be more discerning about which stocks they invest in.
To add to the woes of the hyperscalers, Amazon has filed an SEC disclosure about potentially raising equity and debt to fund the buildout.
And just yesterday, Google raised $32B in debt in under 24 hours, including a 100-year sterling bond: the first century bond from a tech company since the dot-com era. The company that generated $73B in free cash flow last year is now issuing century bonds to fund AI infrastructure.
This is a genuine regime shift for how these companies get valued. FCF yields compress, debt rises, and the market (quite rationally) reprices accordingly.
But here’s the other side of that coin, and it’s the side that matters for our thesis:
The cash leaving hyperscaler free cash flow statements doesn’t vanish. It becomes revenue for the companies sitting downstream in the infrastructure stack.
The capex that compresses Google’s FCF yield is the same capex that fills order books for memory vendors, networking companies, cooling providers, and power infrastructure builders.
Conclusion: The hyperscaler pain is the infrastructure opportunity we alluded to in our 2026 Outlook. So while the market is looking at near-term FCF compression, we’re looking at revealed preference, and what the largest cheque-writers in the world are telling us with their actions.
The receipts
In our 2026 Outlook (Part 1), we projected 2025 capex using guidance ranges and run-rate analysis. The result: actuals came in at $448B, exceeding the guidance-based total of $421-430B and landing squarely within our run-rate estimate of $440-450B. Microsoft overshot its own guidance by 18%, Amazon by 6%. Every hyperscaler trended at or above targets, exactly as we called.
Table 3: 2025 Projections vs Actuals
Source: Deep Edge Research 2026 Outlook (Part 1), public filings
Conclusion: The projections were only half of what we wrote. The directional thesis was the other half. From our 2026 Outlook Part 1 we wrote: “When the largest cheque-writers in the world are all overshooting their own guidance, that is not narrative. That is revealed preference — and it tells you what they see coming in 2026 (and beyond)”. What they see coming is now here. And it’s bigger than even we expected.
The 2026 step-change
Aggregate 2026 guidance came in at $670-715B, blowing past the Street consensus of $530-545B by 27-35%.
Google shocked at $175-185B (46-55% above estimates).
Amazon guided $200B (36% above).
Even the most conservative surprises, Meta and Oracle, exceeded consensus by double digits.
Table 4: 2026 Capex Guidance vs Wall Street Consensus
Notes: Oracle FQ3 earnings expected mid-March; guidance reflects standing estimates.
Source: Deep Edge Research, earnings calls, consensus estimates
Google nearly doubled its 2025 spend. Amazon committed to the single largest capex figure ever guided by a public company. These are not incremental step-ups. This is a step-change. And the acceleration is compounding.
Across the five largest infrastructure spenders, aggregate capex has grown from $259B in 2024 to $448B in 2025 to a guided $693B in 2026: a 64% two-year CAGR. Oracle leads at 104%, followed by Google (86%) and Meta (84%).
Table 5: Year-over-Year Acceleration
Source: Deep Edge Research AI Infrastructure spend database (compiled from public filings; includes finance leases)
Conclusion: To be clear, $693B in annual capex spend is the equivalent of Sweden’s GDP. This is not a company story or a sector story. This is an industrial-scale buildout and we are positioned to capture asymmetric upside opportunities.
The Bubble Litmus Test: still passing
In Part 2 of our 2026 Outlook, we highlighted that the AI infrastructure spend, high-though-as-it-may-be, is not a Bubble.
To illustrate this point, we introduced our Bubble Litmus Test (amongst other tests):
In a bubble, supply chases demand that is not there.
In a buildout, demand outruns supply that cannot keep up.
The Q4 earnings cycle just gave us the clearest confirmation yet that we are firmly in the second scenario. All four companies independently reported the same dynamic: Pichai expects to be capacity-limited “through the year,” Jassy said Amazon “could actually grow faster” with more supply, Hood confirmed demand still exceeds what Microsoft can deliver, and Li acknowledged Meta remains “capacity constrained.”
Table 6: Supply Constraint Quotes
Source: Q4 2025 earnings calls (Jan-Feb 2026)
Four independently managed, fiercely competitive companies. Same message. Same constraint.
And the demand isn’t theoretical; it’s sitting in signed contracts:
Google Cloud backlog: $240B (doubled YoY, +55% QoQ)
AWS backlog: $244B (+40% YoY, +22% QoQ)
Microsoft commercial RPO: $625B
When Pichai was asked what keeps him up at night, his answer was telling:
“Capacity — all constraints, be it power, land, supply chain constraints. How do you ramp up to meet this extraordinary demand?”
Conclusion: That is not the language of a bubble. That is the language of a buildout and crucially, a buildout that is diversifying across the stack.
Where the $520B goes
In Part 3 of our 2026 Outlook, we estimated that c. 75% of hyperscaler capex flows into AI infrastructure. At the time, based on $600B in projected total capex, that implied c. $450B.
With the new guidance putting total capex at c. $690B (midpoint), that 75% slice now implies c. $520B in AI infrastructure specific spend for 2026.
The question for investors is not whether the spend is happening. It is where it flows, and which companies sit in the path of that capital.
Our estimates and checks suggest that GPUs and accelerators remain the largest single line at over $200B, but the spend is broadening and collectively account for nearly $300B of the total:
data centre construction ($90B+),
networking and interconnect ($55B+),
neoclouds ($50B+),
memory and storage ($45B+),
cooling ($30B+),
and power infrastructure ($25B+)
Table 7: Where the 2026 AI Infrastructure Capex Goes
Source: Deep Edge Research estimates, informed by vendor disclosures, industry checks, and CreditSights methodology.
Two observations worth highlighting:
1) The GPU line is no longer just NVIDIA. Every major hyperscaler is now investing heavily in custom silicon for inference: Google’s TPU Ironwood (7th generation), Amazon’s Trainium (already a $10B+ ARR business with Trainium 3 supply fully committed through mid-2026), Microsoft’s Maia, and Meta’s own silicon programme. Broadcom (AVGO) is a key enabler in the custom ASIC ecosystem. This is not a threat to NVIDIA’s training dominance; it is an expansion of the total addressable market as inference becomes a workload in its own right, exactly as we described in 2026 Outlook Part 1.
2) The spend broadens beyond the chip. GPUs and data centre construction are the two largest lines (c. $290B combined, or roughly 55% of the total), but you cannot get usable GPU-hours without the memory to feed the chip, the network to coordinate the cluster, the cooling to manage density, and the power to keep the lights on. Every category in the table above is part of the same system, and a constraint in any one of them limits throughput for the entire system. Meanwhile, neoclouds and compute platforms represent the fastest-growing slice: when hyperscalers can’t build fast enough, overflow demand lands with third-party providers who already have power infrastructure and data centre capacity.
Conclusion: This is why we keep saying: exposure to the buildout is not the same as capturing the economics. The companies that benefit most won’t just be “in the AI supply chain”; they’ll be the ones sitting on binding constraints with pricing power.
What we’re watching
These are the signposts that decide whether this remains a TAKE or flips to a BREAK:
Supply constraint language: Does it persist through Q1 2026 earnings? If any hyperscaler shifts from “capacity build” to “optimise or pause,” that’s a regime signal.
Backlog trajectory: Google Cloud ($240B) and AWS ($244B) are at record highs. A sequential decline, without supply constraints as the explanation, would be a warning.
Capex execution vs guidance: $670-715B is guided, not spent. We will be watching for execution delays, particularly power and land constraints pushing timelines right.
Token and usage proxies: Inference workloads should continue compounding. We will be watching Google’s tokens/minute (currently 10B/min) and Microsoft’s Foundry adoption.
Custom silicon traction: Does Amazon’s Trainium business (>$10B ARR, triple-digit growth) sustain? Do Google’s TPU deployments scale? This tells us whether inference demand is genuinely broadening the accelerator market beyond NVIDIA.
Regulatory and geopolitical risk: Export controls, power permitting delays, or antitrust scrutiny of hyperscaler concentration could slow execution. At $700B, even a 10% shortfall is $70B of demand that doesn’t materialise.
Bottom line
The sticker shock last week was real and the market is still flinching at the size of the cheques. We’re not concerned; we are looking at the underlying mechanics and downstream beneficiaries instead. Our thesis logic is still intact:
$670-715B in 2026 capex guidance.
Every hyperscaler supply-constrained.
Cloud backlogs at record highs.
A 64% two-year CAGR in aggregate infrastructure spend.
And crucially, the language from management is not “invest and hope” but “build as fast as we can to meet demand that is already there.”
Our 2026 Outlook thesis, that AI infrastructure is a buildout, not a bubble, and that spend broadens across the system, just received its strongest validation yet.
As we mentioned in the Outlook, the question is no longer whether the buildout is happening. It is who captures the economics as it scales.
On Friday, we’ll publish a detailed breakdown of the AI infrastructure landscape: the companies sitting in the path of this $520B, how our screening pipeline evaluates them, and where we see the most asymmetric risk/reward across the stack.